From: lk50 on 14 Jan 2010 04:40 Hi there, How do I show resource initials on the gantt chart rather than their full names? Many thanks -- lk50 ------------------------------------------------------------------------ lk50's Profile: http://forums.techarena.in/members/87282.htm View this thread: http://forums.techarena.in/microsoft-project/1293061.htm http://forums.techarena.in
From: Rob Schneider on 14 Jan 2010 06:12 Right mouse click on the Gantt Chart, and pick Bar Styles. Find the row for task (to which the names are attached). Show the Text tab at botton, and pick "Resource Initials" instead of "Resource Names". There is a Help button on that dialog box for more information. --rms www.rmschneider.com On 14/01/10 09:40, lk50 wrote: > Hi there, > > How do I show resource initials on the gantt chart rather than their > full names? > > Many thanks > >
From: lk50 on 14 Jan 2010 08:09 Thanks for you help on this Rob -- lk50 ------------------------------------------------------------------------ lk50's Profile: http://forums.techarena.in/members/87282.htm View this thread: http://forums.techarena.in/microsoft-project/1293061.htm http://forums.techarena.in
From: Trevor Rabey on 14 Jan 2010 05:51 Easy. Format, Bar Styles. You see a text tab and a bars tab in the lower half. Text tab. Choose any field for the right end of the bar, or on top or under or inside. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "lk50" <lk50.44rxrc(a)DoNotSpam.com> wrote in message news:lk50.44rxrc(a)DoNotSpam.com... > > Hi there, > > How do I show resource initials on the gantt chart rather than their > full names? > > Many thanks > > > -- > lk50 > ------------------------------------------------------------------------ > lk50's Profile: http://forums.techarena.in/members/87282.htm > View this thread: http://forums.techarena.in/microsoft-project/1293061.htm > > http://forums.techarena.in >
|
Pages: 1 Prev: MS Project Master Project Resource Allocation Next: Import MS-Access 2007 |