From: Milan Bortel on
Hi Julie,

I guess I'll give up on this issue... Just wait on Windows 7 to be installed
as standard in our training center... Hope it's because of XP fault.

Thnx for post,

--
Milan Bortel

MCAS, MCTS
GOPAS Computer Training Center
Brno, Czech Republic


"JulieS" wrote:

> I cannot reproduce here either using Project 2007 SP-2 installed to
> XP SP-3. There have been a number of hotfixes that were released
> since SP-2. In a quick scan I didn't see anything specific to this
> issue, but you may want to take a look yourself. To the best of my
> recollection, I do not have any of the hotfixes post SP-2 installed.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
>
>
> "Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote in
> message news:C0C531D1-8401-46E2-9431-162CF31A3D19(a)microsoft.com...
> > Ouch...
> >
> > I installed SP2, but it didn't help!!
> >
> > What comes next? Is there any available patch which is not
> > included in SP2
> > and could help?
> >
> > Thnx guys.
> >
> > Milan
> >
> >
> > "Milan Bortel" wrote:
> >
> >> Hi Mike,
> >>
> >> it's like this - we have 12 computers in class and the bug occurs
> >> on every
> >> pc, no matter what project file you have opened. Even in new
> >> created ones.
> >>
> >> So I guess it's the Project fault.
> >>
> >> We'll try to install SP2 and see if it helps.
> >>
> >> I'll let you know.
> >>
> >> --
> >> Milan Bortel
> >>
> >> MCAS, MCTS
> >> GOPAS Computer Training Center
> >> Brno, Czech Republic
> >>
> >>
> >> "Mike Glen" wrote:
> >>
> >> > Hi Milan,
> >> >
> >> > When you say it works on another PC, is that with the same
> >> > project?
> >> >
> >> > We need to discover whether your project is at fault, whether
> >> > it is
> >> > Project at fault, or whether it's your PC. Does the symptom
> >> > occur with
> >> > other projects on this PC? Does it occur with this project on
> >> > other PCs?
> >> > Does it occur with other projects on other PCs?
> >> >
> >> > FAQs, companion products and other useful Project information
> >> > can be seen
> >> > at this web address: <http://www.mvps.org/project/>
> >> >
> >> > Hope this helps - please let us know how you get on :-))
> >> >
> >> > Mike Glen
> >> > MS Project MVP
> >> >
> >> >
> >> >
> >> > "Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote in
> >> > message
> >> > news:44DA4529-7893-40E8-AD84-9136737E9445(a)microsoft.com...
> >> > > I tried to type N/A instead of keeping it blank but that
> >> > > doesn't work
> >> > for me...
> >> > >
> >> > > (on other pc it works perfectly...)
> >> > >
> >> > > Milan
> >> > >
> >> > > "Projectability" wrote:
> >> > >
> >> > >> Have you tried putting in N/A for the second available to
> >> > >> period - if
> >> > you
> >> > >> leave it blank this may be causing the problem.
> >> > >>
> >> > >> --
> >> > >> Dominic Moss
> >> > >>
> >> > >> Projectability - Helping People achieve more with Microsoft
> >> > >> Project
> >> > >>
> >> > >> Check the Downloads section on our Website for useful
> >> > >> documents on both
> >> > >> Project Management and Microsoft Project
> >> > >>
> >> > >> www.projectability.co.uk
> >> > >>
> >> > >> Why not subscribe to our monthly newsletter for hints tips
> >> > >> and views
> >> > >>
> >> > >>
> >> > http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFt
> >> > fgVw%3D%3D
> >> > >>
> >> > >>
> >> > >>
> >> > >>
> >> > >>
> >> > >> "Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote
> >> > >> in message
> >> > >> news:D7A986D3-A863-424B-ACC5-8E95261D45F5(a)microsoft.com...
> >> > >> > Hi,
> >> > >> >
> >> > >> > I got really weird bug when trying to set resource
> >> > >> > availability
> >> > changing
> >> > >> > by
> >> > >> > date in MSP 2007.
> >> > >> >
> >> > >> > Situation:
> >> > >> > default - available from (N/A), available to (N/A), units
> >> > >> > (100%)
> >> > >> >
> >> > >> > change -
> >> > >> > 1) available from (N/A), available to (12/31/2009), units
> >> > >> > (100%)
> >> > >> > 2) available from (1/1/2010), available to (keep this
> >> > >> > blank), units
> >> > (50%)
> >> > >> >
> >> > >> > When I type in the 50% value it works correctly, but when
> >> > >> > I try to
> >> > fill in
> >> > >> > the value using the spinner instead - MSP crashes.
> >> > >> >
> >> > >> > Any ideas why?
> >> > >> >
> >> > >> > --
> >> > >> > Milan Bortel
> >> > >> >
> >> > >> > MCAS, MCTS
> >> > >> > GOPAS Computer Training Center
> >> > >> > Brno, Czech Republic
> >> > >>
> >> > >>
> >> > >> .
> >> > >>
> >> >
>
>
> .
>
From: Milan Bortel on
Rob,

we have standard images, which we install "fresh" on each course. And even
on new installed image this bug appears.

It works on my home pc correctly, though.

Probably it's something between XP and MSP... reinstalling MSP didn't help,
installing SP2 didn't work either.

As I said to JulieS.... Will wait for Win7 to come (it's matter of few
weeks) and hope it works..

--
Milan Bortel

MCAS, MCTS
GOPAS Computer Training Center
Brno, Czech Republic


"Rob Schneider" wrote:

> Hunch: It's probably not a bug in Project as others in world would have
> seen this by now. Maybe the will fix if the flawed file is updated.
> It's surely something with your installation of Project, Windows, and
> whatever.
>
> try:
>
> : reinstall Project
> : install Project with all SP's on a "fresh" Windows machine (not
> touched by your students)
>
> You previously said that it worked on one machine. That machine now no
> longer working? What changed. Or what is different about that machine?
>
> --rms
>
> www.rmschneider.com
>
>
>
>
>
> Milan Bortel wrote:
> > Hi Mike,
> >
> > it's like this - we have 12 computers in class and the bug occurs on every
> > pc, no matter what project file you have opened. Even in new created ones.
> >
> > So I guess it's the Project fault.
> >
> > We'll try to install SP2 and see if it helps.
> >
> > I'll let you know.
> >
> .
>
From: Rob Schneider on
is the 'image' flawed? who made it?

--rms

www.rmschneider.com





Milan Bortel wrote:
> Rob,
>
> we have standard images, which we install "fresh" on each course. And even
> on new installed image this bug appears.
>
> It works on my home pc correctly, though.
>
> Probably it's something between XP and MSP... reinstalling MSP didn't help,
> installing SP2 didn't work either.
>
> As I said to JulieS.... Will wait for Win7 to come (it's matter of few
> weeks) and hope it works..
>
From: JulieS on
Hello Milan,

I don't think it's an issue with Windows XP, as I am running on XP
Pro (XP-3) and can't reproduce. Anyway, good luck and if you
discover the root of the problem, post back if you can.

Julie

"Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote in
message news:8361D890-AFD4-4731-8D9C-0A0E379987B5(a)microsoft.com...
> Hi Julie,
>
> I guess I'll give up on this issue... Just wait on Windows 7 to be
> installed
> as standard in our training center... Hope it's because of XP
> fault.
>
> Thnx for post,
>
> --
> Milan Bortel
>
> MCAS, MCTS
> GOPAS Computer Training Center
> Brno, Czech Republic
>
>
> "JulieS" wrote:
>
>> I cannot reproduce here either using Project 2007 SP-2 installed
>> to
>> XP SP-3. There have been a number of hotfixes that were released
>> since SP-2. In a quick scan I didn't see anything specific to
>> this
>> issue, but you may want to take a look yourself. To the best of
>> my
>> recollection, I do not have any of the hotfixes post SP-2
>> installed.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>>
>> "Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote in
>> message
>> news:C0C531D1-8401-46E2-9431-162CF31A3D19(a)microsoft.com...
>> > Ouch...
>> >
>> > I installed SP2, but it didn't help!!
>> >
>> > What comes next? Is there any available patch which is not
>> > included in SP2
>> > and could help?
>> >
>> > Thnx guys.
>> >
>> > Milan
>> >
>> >
>> > "Milan Bortel" wrote:
>> >
>> >> Hi Mike,
>> >>
>> >> it's like this - we have 12 computers in class and the bug
>> >> occurs
>> >> on every
>> >> pc, no matter what project file you have opened. Even in new
>> >> created ones.
>> >>
>> >> So I guess it's the Project fault.
>> >>
>> >> We'll try to install SP2 and see if it helps.
>> >>
>> >> I'll let you know.
>> >>
>> >> --
>> >> Milan Bortel
>> >>
>> >> MCAS, MCTS
>> >> GOPAS Computer Training Center
>> >> Brno, Czech Republic
>> >>
>> >>
>> >> "Mike Glen" wrote:
>> >>
>> >> > Hi Milan,
>> >> >
>> >> > When you say it works on another PC, is that with the same
>> >> > project?
>> >> >
>> >> > We need to discover whether your project is at fault,
>> >> > whether
>> >> > it is
>> >> > Project at fault, or whether it's your PC. Does the symptom
>> >> > occur with
>> >> > other projects on this PC? Does it occur with this project
>> >> > on
>> >> > other PCs?
>> >> > Does it occur with other projects on other PCs?
>> >> >
>> >> > FAQs, companion products and other useful Project
>> >> > information
>> >> > can be seen
>> >> > at this web address: <http://www.mvps.org/project/>
>> >> >
>> >> > Hope this helps - please let us know how you get on :-))
>> >> >
>> >> > Mike Glen
>> >> > MS Project MVP
>> >> >
>> >> >
>> >> >
>> >> > "Milan Bortel" <MilanBortel(a)discussions.microsoft.com> wrote
>> >> > in
>> >> > message
>> >> > news:44DA4529-7893-40E8-AD84-9136737E9445(a)microsoft.com...
>> >> > > I tried to type N/A instead of keeping it blank but that
>> >> > > doesn't work
>> >> > for me...
>> >> > >
>> >> > > (on other pc it works perfectly...)
>> >> > >
>> >> > > Milan
>> >> > >
>> >> > > "Projectability" wrote:
>> >> > >
>> >> > >> Have you tried putting in N/A for the second available to
>> >> > >> period - if
>> >> > you
>> >> > >> leave it blank this may be causing the problem.
>> >> > >>
>> >> > >> --
>> >> > >> Dominic Moss
>> >> > >>
>> >> > >> Projectability - Helping People achieve more with
>> >> > >> Microsoft
>> >> > >> Project
>> >> > >>
>> >> > >> Check the Downloads section on our Website for useful
>> >> > >> documents on both
>> >> > >> Project Management and Microsoft Project
>> >> > >>
>> >> > >> www.projectability.co.uk
>> >> > >>
>> >> > >> Why not subscribe to our monthly newsletter for hints
>> >> > >> tips
>> >> > >> and views
>> >> > >>
>> >> > >>
>> >> > http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFt
>> >> > fgVw%3D%3D
>> >> > >>
>> >> > >>
>> >> > >>
>> >> > >>
>> >> > >>
>> >> > >> "Milan Bortel" <MilanBortel(a)discussions.microsoft.com>
>> >> > >> wrote
>> >> > >> in message
>> >> > >> news:D7A986D3-A863-424B-ACC5-8E95261D45F5(a)microsoft.com...
>> >> > >> > Hi,
>> >> > >> >
>> >> > >> > I got really weird bug when trying to set resource
>> >> > >> > availability
>> >> > changing
>> >> > >> > by
>> >> > >> > date in MSP 2007.
>> >> > >> >
>> >> > >> > Situation:
>> >> > >> > default - available from (N/A), available to (N/A),
>> >> > >> > units
>> >> > >> > (100%)
>> >> > >> >
>> >> > >> > change -
>> >> > >> > 1) available from (N/A), available to (12/31/2009),
>> >> > >> > units
>> >> > >> > (100%)
>> >> > >> > 2) available from (1/1/2010), available to (keep this
>> >> > >> > blank), units
>> >> > (50%)
>> >> > >> >
>> >> > >> > When I type in the 50% value it works correctly, but
>> >> > >> > when
>> >> > >> > I try to
>> >> > fill in
>> >> > >> > the value using the spinner instead - MSP crashes.
>> >> > >> >
>> >> > >> > Any ideas why?
>> >> > >> >
>> >> > >> > --
>> >> > >> > Milan Bortel
>> >> > >> >
>> >> > >> > MCAS, MCTS
>> >> > >> > GOPAS Computer Training Center
>> >> > >> > Brno, Czech Republic
>> >> > >>
>> >> > >>
>> >> > >> .
>> >> > >>
>> >> >
>>
>>
>> .
>>