ms project 2000 resource calendar
when I change a resources calendar to reflect vacation, tasks that have been assigned during that time do not move. ... 23 Jun 2005 12:10
mpp - mpx files
Hi All, Does anycone know how I can get new versions of microsoft project to save a file in mpx format. I have an existing application that reads mpx files and wondered if there was a way I could convert mpp to mpx. Chris ... 21 Jun 2005 05:27
STDOLE2.TLB error message when opening Project
I get the following error message every time Microsoft Office Project 2003 Standard (happens with and without SP1 installed). The file "STDOLE2.TLB" cannot be found or contains a Visual Basic for Applications library that is not valid. Verify that the file name is correct, and then try again. If the Visual... 15 Jun 2005 17:08
Locked out of Enterprise Resource Pool
I receive the error "The enterprise resource cannot be checked out at the moment. Please try it again later" when modifying enterprise resources under Admin. I had our database administrator change the PROJ_CHECKEDOUT field to zero to see if the problem was that it was checked out, but that didn't work. ... 9 Jun 2005 17:40
Project error
hi everyone i 've a problem with project 2003; i've removed project 2000 and install 2003 pro, but when i start the program i receive the following error " Database upgrade utility1004 An unexpected error occurred with the method. My O.S is w2k sp3, if i gain acces to the system with a new user the message doesn... 6 Jun 2005 03:26
How do I unhide a column?
I have hidden a column in MS Project. How do I unhide it. I try to select the columns surrounding the hidden column and right click but there is not an option for unhide. Thanks Chris ... 27 May 2005 11:01
Question with MS Project on free slack and critical path
Why do the 0 days on free slack not also show up as a red line on the gantt chart as a critical path? Thanks Randy ... 23 May 2005 12:37
Elapsed time calculations
People, Last week a poster asked for a method of finding the number of elapsed days between two dates in Project. I, being bold and brave, answered with a simple formula that could be used with a customized duration field. The formula was: Duration1 = DateDiff("d",[Start],[Finish])*480 The factor of "480" is n... 12 Mar 2005 12:36
MS Project - Wrap
This is the question I want to ask Microsoft in regard to MS Project. There is an option to print a report under "Assignments" called "To-do List " When I print this report it cuts off the "task name" information and it seems to be limited to 85 characters appearing in that column on the report. I would l... 7 Mar 2005 17:13
MS Project 2003 Error on Startup: Database Upgrade Utility 1004
I just installed MS Project 2003 and had previously install Project 2000. Everytime I open the Project 2003 application I receive an error: "Database Upgrade Utility 1004 An unexpected error occurred with the method". How can I fix this? ... 2 Mar 2005 18:32