calculation How does BCWP,BCWS and ACWP calculated in ms project? What is the difference between them? plz help me. thnks in advance. ... 27 Sep 2005 16:02
Missing File- Urgent Dears, I installed a project Professional on a client computers,some users can not install speech recognitions tools,it states that there is a missing file (SKU01F.CAB) ! did any body face this issue ? and how i can find this missing file ! -- PMO Specialist ... 29 Sep 2005 15:49
Problem with digital signature Hi, I've bought a code signing digital signature from the Comodo group which I have used successfully to digitally sign macros in Word and Excel (both 2000 and 2003 versions). I now need to sign some macros in MS-Project 2000 and it's failing! I can select the digital signature but, when I save the projec... 26 Sep 2005 12:31
Calendar durations (again) I want to do something really simple and I'm not sure the best way to do it. I've read many of the posts on the subtleties of days per month, calenders etc. All I want to do is say that a particular task starts approximately 12 calendar months after an event. I want to use this to represent an approximate l... 28 Sep 2005 09:39
Baseline in MS Project 2003 I know that only some information is captured when baselining a project. I have looked for a complete list of what is and is not captured but I cannot find it. Does such a list exist, and if so, where is it? Thanks in advance. ... 16 Sep 2005 17:19
Setting up Project for weekend project? I want to set up a MS Project Gant chart to track a weekend project, so I only want to show Saturday and Sunday as the working days. How do I hide non-working hours on a MS Project Gantt Chart? ... 14 Sep 2005 22:26
Cost Variance vs. Actual Costs How do I add the amount of my project's initial budget so that it will be reflected in my Project 2003 Financial reports? As well as, reflect as the Baseline Cost and in the Cost Variance so Project 2003 will correctly calculate my project's budget & cost? Thanks, -- vsinc ... 11 Sep 2005 09:50
Exporting MS Project 2003 to Primavera...? How can i export MS Project to Primavera...? Thanks in advance... ... 5 Sep 2005 09:49
Definition of Total Cost Actually I'm looking for a variable that is the labor/resource costs but can't find one so am thinking about using "total cost" aka "cost" minus "fixed costs". Does anyone have the definition of "total cost" so I can see if my plan should work? Thank you, Peter ... 3 Sep 2005 10:53 |