First  |  Prev |  Next  |  Last
Pages: 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71
Macro for filter
Dear sir , I have just started learning macros.I want to creat a macro for " Late " activities in the "Status " column. When I complete the procedure and go to VBE , there the steps end at Autofilter.It just creats filter but next procedure it doesn't take.Even if when I write Autofilter Selecttaskc... 27 Jan 2010 04:52
custom columns for WKS
I would like to create a formula in a custom field that tells me what week my start date is in. I have my gantt set up to show WK1, WK2, etc. I would like to have that same week designation in a custom column. Can I do that? thanks. Penny ... 2 Feb 2010 17:34
how do i reset the Unique ID field in Project 2003?
Cutting and pasting causes all kinds of problems. The simple need, when starting a new project file from another is to reset the Unique IDs and then baseline the file everywhichway. Any seasoned PM would know the value of this. This should be the default option when a new MPP is saved from a template. "Rod G... 26 Jan 2010 16:41
Formatting 'Hours' in work field with out decimals
I need help in formating the work hours showing rounded off to next hr, rather than showing with one decimal. Appreciate help ... 27 Jan 2010 04:52
How to Copy Macros
When I open a MSP File on another machine I lose all the macros and settings. Is there a way to copy the macros and also the settings? ... 26 Jan 2010 16:41
Can I link my Project with my Blackberry?
Is there a way to some how sync my ms project with my blackberry? ... 2 Feb 2010 17:34
Calendar View - Display Resource Name
Jan, Soooo sorry for the late response. This is exactly what I needed. THANKS ! MarkP "Jan De Messemaeker" wrote: Hi, Calendar View Format Menu Bar Styles Select All In text, replace Name by Resource Names HTH -- Jan De Messemaeker Microsoft Project Most Valua... 26 Jan 2010 12:06
Maintain tasks close to each other
I have 2 tasks that must be done in sequence and in a consecutive way. How can I force Project to keep them close to each other during the resource level phase? Thanks. Bye Franco ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ http://www.francolombardo.net Scala, Java, As400..... http://twitter.com/f_lombardo ~~~~~... 2 Feb 2010 17:34
Resource usage view as a Web report
I would like to save the project with a custom view similar to Resource Usgage view with Resources in a Row, and columns showing the Work / week. (PS: I am familiar wtih time phased view, which can be exported to Excel, -- is this the only way to show this in Excel or Is there a way to save as Web Page) -- Than... 26 Jan 2010 15:33
Duration fixed and Work fixed
Hello, I need to do one taks with "duration fixed AND Work Fied" is this possible ? I need that dont move duration and work but units be variable.. I cant. Sorry my english and thanks in advance, Christian W ... 26 Jan 2010 10:58
First  |  Prev |  Next  |  Last
Pages: 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71