earn value management
Right after I baseline my project, if I run a Earn Value Management report, my EV, AC and PV are different. I would have expect that all those values would be the same. Why is it not? ... 19 May 2010 10:28
I need a MS Project 2007 Kick Start
Let's say I am painting a car in a shop and I have three painters. I have my cost and my resources all filled out. The Gantt Chart is fine, then for no reason the hours needed to not match the days it will take to complete a project. Example: I have 6 hours per day per person, I have a 24 hour project with three peopl... 18 May 2010 14:48
Difference b/w WINDOWS 2007 professional and 2007 standard os
Please update me with the difference b/w WINDOWS 2007 professional and 2007 standard OS. ... 17 May 2010 19:08
formulas for Actual Duration and BCWP
I have yet to be able to figure out the formulas that derive both Actual Duration and BCWP when using actual data in my plans. I understand from where the data is to come, but I have not found a consistent set of formulas I can use to calculate Actual Duration, which is essential to calculating % Complete...no... 17 May 2010 18:01
Highlight a Date in Project 2003?
When you add any drawing (such as a line) to a Gantt chart, you can right-click it and select Properties. On the Size and Position tab select the ID of your milestone and the line will move whenever the task bar moves. Alternatively, I always have a Deliverables Summary Tasks at the very top of my schedules an... 17 May 2010 16:55
Printing Reports
I create a report, but can't print it. Printers box is grayed out. Is there an option that has disabled printing from print preview? ... 17 May 2010 20:14
Password Protection Error
I put a write password on my project file. When I open it I get prompted for read-only which I select. However, it gives me an error that the file has too many rows, suggest to delete some or put in subreports. My file has no database, only 37 rows, I'm using 2007 with all the updates. If i take off the wri... 20 May 2010 16:08
Highligt a Date in Project 2003?
I have many Milestones that are very important in my Project, how can I highligt these Milestones over all the project? When I used to make Grantt charts in Excel I used to put a vertical line over all the projet but with Project 2003 if you use a line the line moves from the original position. Is there a way ... 19 May 2010 10:28
Date Functions
I am having problems getting the syntax correct for the DateDiff function. Help states that it's DateDiff (interval,date1,date2). If I want the resulting interval in days, what do I enter? Thanks ... 17 May 2010 12:26
show task notes as either a report or in outlook calender
Hi there guys I am working on Project 2007 and Office 2007 I am wanting to know how I can retrieve the tasks' notes on a daily basis, either as a report or if it can be sent to outlook's calender (as a task or within the calander) I can set reminders easy enough that bring in the task to outlook but it doe... 18 May 2010 06:00